A piece of work takes 20 labourers to complete in 10 days. how many labourers will complete the same job in 25 days if they work at the same rate?​

Respuesta :

denimjackets23
denimjackets23 denimjackets23
  • 04-09-2021

Step-by-step explanation:

If 20 labourers=10 days

x labourers = 25 days

10x= 25×20

[tex] \frac{10x}{10} = \frac{25 \times 20}{10}[/tex]

Cancelling out by 10 on both sides

[tex]x = \frac{25 \times 2}{1} \\ x = 50 [/tex]

Therefore, it takes 50 labourers to complete the work at the same rate in 25 days.

Answer Link

Otras preguntas

How did king james 1 important to the survival of the Jamestown settlers
What motivated Europeans to begin looking to distant lands?
what is 12,430,090 in expanded form
a number is k units to the left of 0 on the number line. describe the location of its opposite.
For what reason was the "Union Party" created? Who were its candidates?
arrange following numbers in increasing order 2.3,45.1,18.735,0.9862,7
what is the complete subject in the following sentence? the young boy rode the bus to school.
How do you translate "fifty-three plus four times c is as much as 21" in an equation
800 is 10 times as much as_____
one egg carton holds 12 eggs .how many cartons  are you able  to fill with 60 eggs.help me please.